One of the worse case in engineering field that we cope with it , was this project , unfortunately because of lack of structural spacing , many clash and engineering problem happen in modeling .Our engineering team working on MEP Discipline.
we drawing all content and system by high accurate for find all problems and prepare 55 page report from Clashes on the other side some mechanical Calculation was wrong and our engineering team try to fine some remedies for that but finally after 6 month we took decision to send project for revision totally .
Bulit 220 Vendor family
17 Floor – Each floor 4200 Sqm